## **Gujarat Electricity Regulatory Commission – Daily Order**

**Case Title:** *Gujarat Urja Vikas Nigam Limited (GUVNL) vs. Gujarat State Electricity Corporation Limited (GSECL)*
**Petition No.:** 2459 of 2025
**Date of Order:** 22 July 2025
**Bench:** Shri Mehul M. Gandhi (Member), Shri S. R. Pandey (Member)
**Location:** Gandhinagar

### **Matter**

Petition filed under **Section 86(1)(b) read with Section 62 of the Electricity Act, 2003** seeking approval of the Commission for the **Supplemental Power Purchase Agreement (PPA) dated 18.02.2025**, extending the original **PPA dated 07.01.2010** for transferred power stations of **2912 MW capacity**.

The extension sought is for a further period **up to 01.04.2030 or the actual useful life of the plants, whichever is earlier**.

### **Parties**

* **Petitioner:** Gujarat Urja Vikas Nigam Limited (GUVNL)

* Advocates: Mr. Nilay Joshi, Ms. Rashmi Fumakiya

* **Respondent:** Gujarat State Electricity Corporation Limited (GSECL)

* Advocates: Mr. Shubhadeep Sen, Mr. Nitin Kansara, Mr. P.A. Parekh, Mr. H.N. Bhatt

### **Hearing Proceedings (18 July 2025)**

1. **Petitioner’s Submissions:**

* Confirmed filing of the petition under Section 62 and 86(1)(b).
* Agreed to issue **public notices in newspapers** inviting comments/suggestions/objections from stakeholders.

2. **Respondent’s Submissions (GSECL):**

* Reply not yet filed; directed by Commission to file within **4 weeks**.

### **Commission’s Observations & Directions**

* The petition relates to procurement of power under a Supplemental PPA, hence requires **stakeholder consultation**.

* Directed Petitioner (GUVNL) to:

* Issue **public notices** in **two Gujarati dailies** and **one English daily**.
* Upload petition & documents on its website.
* Invite stakeholder comments within **30 days** of notice.
* File compliance affidavit with published copies of notices.

* Commission staff also directed to upload the petition on GERC website and share stakeholder submissions with both parties.

* **Timelines set:**

* Respondent (GSECL) – 4 weeks to file reply.
* Petitioner (GUVNL) – 3 weeks thereafter to file rejoinder.

### **Order**

* Petition admitted; public consultation ordered.
* Next hearing date to be intimated separately.

**Signed:**

* Sd/- Shri S. R. Pandey (Member)
* Sd/- Shri Mehul M. Gandhi (Member)

**Place:** Gandhinagar
**Date:** 22.07.2025