## **Case Summary – Gujarat State Electricity Corporation Ltd. (GSECL) vs. Gujarat Urja Vikas Nigam Ltd. (GUVNL)**
**Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar
**Petition No.:** 2507 of 2025
**Order Date:** 08 August 2025
**Coram:**
* Mehul M. Gandhi, Member
* S.R. Pandey, Member
—
### **1. Case Background**
* **Petitioner:** Gujarat State Electricity Corporation Limited (GSECL)
* Counsel: Mr. Shubhadeep Sen, Mr. Nitin B. Kansara
* **Respondent:** Gujarat Urja Vikas Nigam Ltd. (GUVNL)
* Counsel: Mr. K.N. Brahmbhatt, Mr. Kishore Lakhani
* **Nature of Petition:** Filed under **Sections 62 & 86(1)(a) of the Electricity Act, 2003** seeking determination of tariff for **35 MW Solar PV Power Project** at **Khandiya, District Surendranagar**, developed by GSECL.
—
### **2. Petitioner’s Submissions**
* Project commissioned in phases:
* 17.57 MW – 19.03.2022
* 8.14 MW – 05.07.2022
* 9.435 MW – 10.08.2022
* Requested **interim tariff @ 95%** of claimed tariff to cover O\&M and obligations pending final tariff determination.
* Agreed to file within 2 weeks:
* EPC, civil, and O\&M contracts
* Loan agreements & board resolutions for equity
* Copy of PPA, technical details, project particulars
* Agreed to issue **public notice** inviting stakeholder comments.
—
### **3. Respondent’s Submissions**
* Sought **time to file reply** in the matter.
—
### **4. Commission’s Observations & Directions**
* GSECL is a generating company; GUVNL is a licensee – matter falls under Commission’s jurisdiction.
* Directed Petitioner to:
* Issue **public notice** in 2 Gujarati + 1 English newspaper with petition details & invite stakeholder objections within 30 days.
* Upload petition and documents on its website for stakeholder access.
* File compliance affidavit with published notices.
* Directed Commission staff to:
* Upload petition on GERC website.
* Forward received stakeholder objections to Petitioner and notify objectors for hearing.
* Directed Respondent (GUVNL) to file reply within **4 weeks** (copy to Petitioner).
* Petitioner allowed to file rejoinder within **3 weeks** thereafter (copy to Respondent & objectors).
* On **interim tariff request (95%)**, Commission held parties should act as per existing **PPA terms** for energy payments.
* Next hearing date to be intimated separately.
—
### **5. Outcome**
* **Type of Order:** Procedural / Interim directions
* **Effect:** Public consultation process initiated; timelines set for reply, rejoinder, and stakeholder objections.
* Interim tariff not granted – parties to continue under PPA terms.
—