
In the matter of the GERC (Electricity Supply Code and Related Matters) and (Conduct of Business) Regulations for availing 7000 KVA Contract Demand and Consequential Directions – EQ
Summary:
—
## **Case Summary**
**Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar
**Petition No.:** 2342 of 2024
**Date of Order:** 19 July 2025
—
### **Parties**
* **Petitioner:** Hindalco Industries Ltd., setting up a greenfield copper manufacturing facility at Waghodia, GIDC, Vadodara, Gujarat.
*Counsel:* Adv. Kaustubha Mishra with Adv. Krishna Patel, Mr. Rohit Dongre, and Mr. Chirag Sharma.
* **Respondent No. 1:** Madhya Gujarat Vij Company Ltd. (MGVCL)
* **Respondent No. 2:** Gujarat Energy Transmission Corporation Ltd. (GETCO)
*Counsel for both Respondents:* Adv. Ranjitha Ramachandran with others.
—
### **Relief Sought**
Extension of time for completion of works to avail **7000 KVA Contract Demand** from Respondent No. 1 (MGVCL) and related directions.
—
### **Petitioner’s Key Submissions**
1. **Jurisdiction:**
* Dispute involves interpretation of **Regulation 4.33(2)** of the GERC Supply Code, 2015 and **Regulation 9.3(3)** of GERC SOP Regulations, 2005.
* As per **Regulation 1.14** and **9.22** of the Supply Code, GERC has exclusive jurisdiction to adjudicate such disputes.
* Not a “consumer dispute” under Sections 42(5)–(7) of the Electricity Act, 2003; hence CGRF/Ombudsman lack authority.
2. **Regulatory Obligations:**
* Distribution licensee must release bulk-power connections within 180 days after demand note compliance, subject to feasibility and safety. Delays beyond this must be reported to the Commission.
3. **Case Law Support:**
* **Surya Roshni case (Gujarat HC)** – HC remitted a similar matter to the Commission for decision.
* **Reliance Energy (SC)** – State Commission’s authority to direct licensees upheld.
* **BSES Rajdhani Power (APTEL)** – State Commission can regulate and issue directives in case of regulatory violations.
4. **Distinguishing Precedents:**
* Ombudsman orders and other cited cases (e.g., RSPL Ltd. v. PGVCL) are factually different and inapplicable.
—
### **Respondents’ Position**
* Raised a **preliminary issue**: whether the matter falls under CGRF jurisdiction as a consumer–licensee dispute or under the Commission’s specific powers.
* Requested time to file a **consolidated reply** after receiving petitioner’s rejoinder.
—
### **Commission’s Observations & Directions**
* Petition is under relevant sections of the Electricity Act, 2003 and GERC Regulations seeking extension for 7000 KVA demand.
* MGVCL to file consolidated reply within **3 weeks** with a copy to petitioner.
* Petitioner may file a further reply if needed.
* Parties to complete pleadings before the next hearing.
* **Next hearing date** to be intimated separately.
—
**Coram:**
* Shri S.R. Pandey, Member
* Shri Mehul M. Gandhi, Member
—
For more information please see below link: